FERRYCARRIG CIVIL - PENRITH

Ferrycarrig were engaged to install new sewer main and 2 rising mains, the sewer main had a section that needed to be installed under the main rail line requiring to be bored and engaged Bortec Laser Bore to install the sections. The rising main also installed under the main rail line side by side.

1 x 30m bore with 375mm P.P sewer pipe in a 600mm RCJP

2 x 30m bores with 450mm HDPE sewer pipe in a 600mm RCJP