top of page

LEED ENGINEERING - YONGALA

Leed were engaged to install new watermain from Peterborough to Yongala S.A, the watermain had three sections that needed to be installed under the main rail line managed by ARTC. Bortec Laser Bore were engaged to excavate pits, bore under the rail and install the carrier pipe.

2 x 12m bore with 400mm steel casing

1 x 24m bore with 400mm steel casing

Load and Grout 200mm HDPE Pipe in each bore

bottom of page